Project Overview
Project Name | Rumah/Nairiyah Independent Power Project (IPP) 사우디 루마 & 나리야 발전소 건설 프로젝트 |
발주처 | SPPC (Saudi Power Procurement Company) |
Location | Rumah (Central Region) and Nairiyah (Eastern Region), Saudi Arabia |
Capacity | 7,200 MW total (4 plants, 1,800 MW each) |
Technology | Combined-Cycle Gas Turbine (CCGT) with Carbon Capture and Sequestration (CCS) readiness |
Strategic Importance | Part of Saudi Vision 2030 and Saudi Green Initiative; aims for 50/50 energy mix of renewables and gas |
Current Status | Bidding in progress with deadlines extended; pre-qualified bidders list released |
출처: Meed | SPPC sets August deadline for Remah and Al-Nairiyah IPPs